IBS-references_20-01-2020, Download, PDF
FIAC sculpture „Many small cubes“, Paris
- 07/ to 09/2014
- Design for production and installation drawings, support of production
- Main contractor : Galérie Philippe Gravier (archtitecte Sou Fujimoto)
|
|
KAUFLAND Parkhaus, Neckarsulm
- 07/2013 to 05/2014
- Design of metal cladding including production and installation drawings
- Main contractor : Kaufland AG
|
|
SPOT, Oberhausen
- 08/2013 to 01/2014
- Design of metal sheeting including production and installation drawings
- Main contractor : August Heine Baugesellschaft AG
|
|
LAENNEC, Paris
- 07/2012 to 06/2014
- Project management and design of windows
- Main contractor : BOUYGUES Rénovation Privée
- Architects : Valode & Pistre
- Contract sum : 1.8 Mio. €
|
|
CHALLENGER, Ile-de-France
- 04/2011 to 09/2014
- Project management and design (smaller zones) of renovation of facades
- Main contractor : DV construction, member of BOUYGUES group
- Architects : SRA
- Contract sum : 20 Mio. €
|

|
University College London Hospitals (UCLH), London
- 02/2010 to 03/2011
- Project management of facades
- Main contractor : SKANSKA
- Architects : Hopkins & Partner
- Contract sum : 11 Mio. €
|
|
One Hyde Park, London
- 08/2009 to 01/2010
- Support of site management on fully glazed stair cases
- Main contractor : Laing O’Rourke
- Architects : Candy & Candy
- Contract sum : 65 Mio. €
|
|
Tour FIRST (tour AXA), CB 31, Paris
- 04/2008 to 07/2009
- Project management for design of the tower
- Main contractor : BOUYGUES Rénovation Privée
- Architects : KPF
- Contract sum : 35 Mio. €
|
|
Hôpital de Charleroi, Belgium
- 08/2007 to 03/2008
- Project management of facades
- Main contractor : BESIX
- Architects : Art & Built
- Contract sum : 5 Mio. €
|
|
Musée d’Art Moderne, Luxembourg
- 2005 to 2011
- Claim-Management and project management for facades (part time)
- Main contractor ABP
- Architects : Phei & Reuter
- Contract sum : 12.000.000,- €
|
|
F1, Spa-Francochamps
- 2007
- Support of the project management for facades
- Main contractor : BESIX
- Contract sum : 500.000 €
|
|
T1, Paris ( (Headquarter of Suez-GdF))
- 07/2005 to 07/2007
- Project management of facades
- Main contractor : BOUYGUES Construction
- Architects : Valode & Pistre
- Contract sum : 30 Mio. €
|
|
DEXIA-BIL, Headquarter of bank, Esch-Belval (Luxembourg)
- 01/2005 to 06/2005
- Architects : Claude Vasconi
- Mission : Interface between German project management and Main contractor
- Main contractor : DEXIA
- Contract sum : 15 Mio. €
|
|
Le Partitio, Headquarter of French supermarket company, Paris, Pôle Ivry Port
- 01/2004 bis 05/2005
- Mission : Interface between German project management and Main contractor
- Main contractor : Sfica, Paris
- Contract sum : 3.5 Mio. € (double skin)
|
|
- Landesvertretung Niedersachsen/Schleswig-Holstein, Berlin Mitte
- 03/2001 to 12/2001
- Trouble shooting of facades for Main contractor
- Main contractor : Philipp Holzmann AG, Hannover
- Contract sum : 3.5 Mio. DM
- Medienzentrum am Alexanderplatz, Berlin
- 2000
- Project management for design
- Main contractor : Joint Venture Kondor Wessels Berlin GmbH & F.C. Trapp
- Contract sum : 5 Mio. DM
- Israelian Ambassy, Berlin-Schmargendorf, (construction and renovation)
- 2000
- Support of site management and finalizing of cladding works
- Main contractor : Hochtief AG, Berlin
- Contract sum : 5 Mio DM
- Ostbahnhof (ehem. Hauptbahnhof), Berlin Friedrichshain, (construction and renovation)
- 2000
- Support of site management and finalizing of cladding works
- Main contractor : STRABAG AG, Berlin
- Contract sum : 400.000 DM
- Japanese Ambassy, Berlin, (construction and renovation)
- 2000
- site management
- Main contractor : Takenaka Europe
- Contract sum : ca 4 Mil. DM
- ORGA Kartensysteme GmbH, Paderborn, (Neubau eines Bürogebäudes)
- 2000
- Site management for cladding works (aluminium-wood windows)
- Main contractor : Hochtief AG, Bielefeld
- Contract sum : 5 Mio. DM
- Main railway station Köln, (renovation)
- 1999 to 2000
- Support of quality management for Main contractor on site
- Main contractor : ECE G.m.b.H. & Co. KG
- Contract sum : 200 Mio DM
- Shopping mall “Hallen am Borsigturm”, Berlin
- 1998 to 1999
- Project management / interface between French supplier and Main contractor on site
- Main contractor : Herlitz Falkenhöh AG, Berlin
- Architect : Claude Vasconi
- Contract sum : 28 Mio DM
- Europa-Congreßhotel Suhl (ECH), (renovation)
- 1997 to 1998
- Site management for cladding works
- Main contractor : Hochtief AG, NL Suhl
- Architect : Zeidler, Robertship & Partner, Berlin
- Contract sum : 3 Mio DM
- Calenberger Esplanade, Hannover
- 1997
- Site management for cladding works
- Main contractor : STRABAG AG, Hannover
- Architects : GMP
- Contract sum : 5 Mio DM
- Cottbus, (renovation)
- 1996 to 1997
- Site management for cladding works
- Main contractor : GWG “Stadt Cottbus”
- Contract sum : 3 Mio DM
- Lange Straße, Berlin, (renovation)
- 1994 to 1996
- Project and site management for cladding works
- Main contractor : Wohnungsbaugesellschaft Friedrichshain, Berlin
- Architects : Pfannenschmidt, Berlin
- Contract sum : 10 Mio DM